Glazebury WWTW

For this trace heating and thermal insulation contract, ESH supplied and installed a frost protection system to the external plastic water supply pipework.

Tuesday, 26 March 2013

Molson Coors Brewery, Burton On Trent


Molson Coors Brewery is the seventh largest brewer by volume in the world! Here at their Burton-On-Trent headquarters, ESH designed, supplied and install a trace heating system to temperature maintain stainless steel pipework containing caustic soda at between +10°C to +15°C.

Monday, 25 March 2013

St James Hospital, Leeds

On this Raychem specified trace heating project, ESH installed a frost protection system to external pipework using Raychem self regulating heating tape.

NAPP Pharmaceuticals, Cambridge

For this large project, ESH were asked to design, supply and install a frost protection trace heating system to internal sprinkler pipework.

Thursday, 21 March 2013

Good Hope Hospital, Sutton Coldfield


This was our second project within Good Hope after work on the endoscopy and ultrasound roofs back in 2004. This time ESH were contracted to design, supply and install a trace heating system to freeze protect the condense pipework again on the hospital roof.




Wednesday, 20 March 2013

Nottingham Incinerator Plant

Here we were contracted to inspect the heating cable already installed on the hoppers, by testing the circuit for insulation resistance, testing the resistance to determine the heating load and checking the operation of the thermostat.

Thursday, 14 March 2013

7-11 Bishopsgate Offices, London

Within this large (6,000sqm) office building, ESH were contracted to design, supply and install two separate trace heating systems:

  • System one was for the frost protection for the roof mounted BCWS pipework
  • System two for the temperature maintenance of +55°C on the washroom pipework from the basement area up to the 6th floor


Wednesday, 13 March 2013

SAFC Hitech, Wirral

For this process temperature maintenance project, ESH were asked to design, supply and install a trace heating system to maintain +80°C. Type VC constant wattage heating cable was double traced underneath the pipework in order to achieve the required temperature. 

Swinford WTW, Oxford


Within this water treatment works ESH supplied and installed a trace heating system for the frost protection of the external plastic pipework.


Monday, 11 March 2013

Denco Lubrication, Hereford

For this project we supplied and installed a trace heating and thermal insulation system of oil pipework and fittings on two large skids. The purpose of the system was to temperature maintain the pipework at +10°C.

European Centre for Medium Weather Forecasts, Reading



The ECMWF centre is an intergovernmental organisation supported by 34 states based in West London. Here we designed, supplied and installed a trace heating system to provide frost protection to chilled water (flow & return) pipework for a large chiller.



Tuesday, 5 March 2013

Wickham STW

Supplied and installed a trace heating system to frost protect humus de-sludge, humus feed pump station, septic tank area and inlet area pipework.

Monday, 4 March 2013

Sheffield University, Science Administration Building

For this large project, ESH were contracted to design, supply and install two trace heating systems:

  • System one was for the frost protection of the chilled water feed and chilled works system pipework (type VC constant wattage heating cable installed). 